Case Studies
St Mary’s Church
Location:
Whittlebury
Architect:
Stimpson Walton Bond
Contract Duration:
Nov 21 to May 22
Value:
£115,000
Date of Completion:
May 2022
We were awarded main contractor for the works to this Grade II listed building, to oversee/manage and work closely with the architect in the selection of tiles for replacement. Once this had been agreed over 31,000 tiles were removed and replaced with new handmades from Tudor tiles. Works were broken down into 3 phases. Nave being the 1st ,north and south sides , then the chancel and finally the vestry. We had challenging weather throughout this project to overcome, may it be snow, rain or gale force winds, working over a harsh winter season.